Formula of Accident Severity Rate

Similar calculations is ok for industries… Things will get complected when you want to calculate the exact working hours including over time of employees.Timing deductions of employees who were on leave etc.

So better to take the exact working hours with the help of an electronic punching card or let the people dealing with the manpower (Basically HR/ER/IR) calculate the man hour worked and give to safety people for further SR calculations.

Please find the attached file. Hope this helps…

Click Here To Download SR Rate for CiteHR

 

                                  No. of man days lost x 10 6
Severity rate     =  ———————————————-
                                    No. of man-hours worked
Total no of injuries – 12
lost time for injury average – 15 days
Total no of employees – 250
total work hrs in a day 8hrs
weekly 6 working days
so how i can calculate man hours worked per month or year Remove your holidays from the total month days. Ex. 4 sundays deducted from total 31 days. Hence taken as 27 days working days
Deduct any other holidasy in your organization if its there
SR in the Month of Aug’13 317.4603
Similar wise do for year.